DLT Power and Industrial projects
<< Home

Power and industrial projects can benefit greatly from the use of modular construction techniques. Maximising offsite pre-assembly allows the foundations to be installed in parallel with the structure and many elements of the structure to be assembled offsite at the same time. The techniques of transporting and erecting large/heavy sub assemblies are key to the success of these projects.

 

Recent examples of our work include……….

<< Blast furnace re-lining, Taiwan
DLT were sub-contractors for installation of a new 40.75m high 3115 tonne furnace line in Taiwan. Our scope included full engineering of all temporary works required together with supply of jacking equipment and site labour to carry out the work. The blast furnace was delivered to the site in 8 segments, weighing up to 477 tonnes each, which were lifted and skidded into the furnace house before being jacked vertically and aligned for welding. These operations were carried out using a mix of strand jacks and climbing jacks. More>

BARD Offshore 1 wind farm. Transformer platform self-installation system >>
The BARD 1 wind farm is located in the North Sea and has a total of 80 wind turbines producing up to 400 MW which is connected into the german extra-high-voltage grid via a 125km long submarine cable. DLT supplied and operated a 16 x DL-S588 computer controlled strand jack system for the self-installation of the central transformer and accomodation platform. The strand jack system was used to suspend the 3,500 tonne jacket from the floating platform during sea transport, then to lower the jacket down onto the sea bed, and finaly to lift the 3,320 tonne platform up out of the sea into final operating position where it was then structurally connected to the jacket. More>>

<< Steam Drum installations, USA
DLT have provided strand jack systems and site supervision to Rigging International for lifting and installation of a number of steam drums weighing up to 380 te and lifted up to 65 m.  The strand jack system supplied comprises 2 No DL-S418 strand jacks and a DL-L60F/4/350/D diesel powered hydraulic power pack, with a combined lifting capacity of 836 tonnes and a lift speed of 15 m/hour
Pinalito Hydroelectric Plant, Dominican Republic >>
DLT were employed by Odebrecht to supply equipment and site supervision to install a water distribution pipe which was required to pass over one of Dominican's many mountains. DLT's equipment and supervisors assisted in the installation of the pipe, pulling a total of 78 sections, from 10 different locations using DLT strand jacks. The maximum pull was 132 tonnes, and the longest pull 157m. More>
<< Lal-Pir Power Station, Pakistan
DLT were responsible for the design, supply and operation of a system to lift, skid, rotate and lower into final position of a 350 tonne generator.  The generator was delivered outside the building and was lifted off the transporter using 4 No DL-S105 strand jacks mounted on a purpose made transportation frame, which sat on a skid track running into the building.  Once in the building the generator was rotated 90 degrees on a purpose made turntable and skidded a further 10m before being lowered into final position.
Heat exchanger replacement, Indonesia >>
DLT were responsible fore the design, supply and operation of a 60 tonne capacity gantry to replace 2 No 60 tonne heat exchangers from deep within a steel framed structure on PT Peni’s site in Indonesia. Use of these purpose designed gantries in place of conventional cranage avoided the need to extensively dismantle the steel structure to gain access to the vessels, saving time and money.