| Dorman Long Technology | ||
| Blast furnace two relining, China Steel, Kaohsiung, Taiwan |
|
|
|
Each segment was delivered by self propelled modular trailers onto two lifting beams in the slag pit, which were then lifted 14m up to skid track level using 8 No DL-C125 climbing jacks. After lifting each segment was skidded 98m into the furnace house through a temporary opening created in the side of the building, as shown below. |
| |
|
| Once inside the furnace house each segment was lifted and aligned for welding using strand jacks located on two levels as shown below. Eight DL-S185 strand jacks were used at the lower level and eight DL-S418 strand jacks at high level, all monitored and automatically synchronised using the recently developed DL-P40 computer control system. Computer control was critical to the success of these operations, to keep the loads evenly balanced between the ring of eight jacks at each level and to be able to finely adjust the welding gaps between segments to between 1-3mm all around the joint. | |
| |
|
| All eight segments were lifted, skidded and aligned for welding in a period of 24 days, from lifting of the first segment to final positioning of the last segment in the furnace house - requiring a total of 34 seperate lifting and skidding operations. This was achieved through 24 hour working and close co-ordination with the other sub-contractors. The total furnace shutdown period was 94 days. |
|
|
![]() |
| A DLT produced 3D model of the furnace line installation sequence was used to to brief all parties and to assist in the understanding and co-ordination of this complex project. |